The Completion Plan includes all the details of how every benchmark in a Job Plan will be met.
In the E-Myth Mastery Program, the Completion Plan is known across industries as the Action Plan, and is learned in Module 4 on Management.
| # | BENCHMARK | ACCOUNTABILITY OF | DUE BY |
|---|---|---|---|
| 1 | Receive job specifications (specs) from the architect. | Architect | 3 Days prior to 1st Day of Job |
| 2 | Review job specifications for any anomalies or special circumstances. | Foreman | 2 Days prior to 1st Day of Job |
| 3 | Confirm site access with client using the Confirming Site Access With Client script. | Foreman | 1 Day prior to 1st Day of Job |
| 4 | Take the specs to the job site itself. | Foreman | 1st Day of Job |
| 5 | Confirm every measurement and specification with on-site quantification. | Foreman | 1st Day of Job |
| 6 | If there are any discrepancies, fill out a Change Order form for the architect, and an Alert form for the home owner/client. | Foreman | 1st Day of Job |
| 7 | If there are any discrepancies, follow the Consult With Architect and Consult With Client Completion Plans. | Foreman | 1st Day of Job |
| 8 | If there are no discrepancies, follow the Confirm Construction Schedule With Client Completion Plan. | Foreman | 2nd Day of Job |
STANDARDS